Dissertation Halinoja_1313 Errata

Halinoja, M., 2015 Environment Interpretation for Business Continuity in a Project Supplier’s Networks - Critical Factors in International Industrial Upgrades

Department of Industrial Management, Tampere University of Technology, Tampere, Finland

List of errors in the “halinoja_1313”- document:

Missing the word “network”: …each stakeholder has dissimilar network pictures… p. 8 Error in referencing: “Hällgren and Stjernberg (1995)” must be “Hellgren and Stjernberg (1995)” in pages 4, 14, 20, and 49. This error influences also the content and the order in the reference list.

Viittaukset

LIITTYVÄT TIEDOSTOT

Thesis reports the actual project carried out when creating a mechanical test creation environment for EADS Secure Networks. EADS Secure Networks develops professional mobile

Although the SAP Activate methodology itself provides a complete comprehensive package for the project implementation of S/4HANA, some of the critical success factors such as

Information exchange between Fingrid and reserve unit holder is performed in real time and the following information is required by the holder: aFRR up-regulation

The empirical study discovers four crucial factors for benefit realization: the sales phase, the project roles and model, change management, and continuity.. These

Although, Holmen and Pedersen (2003) propose keeping a firm’s network horizon narrow and myopic, a project supplier would benefit from broadening their network

This way implementing Critical Chain Project Management for Catalyst Systems delivery projects would also benefit the research and development project work that many

In summary the most influential attributes, for the overall human resource management process in a multiple project environment, were the reliability and validity of time

The project teams have frequent internal meetings and in the weekly management team meetings the student project managers report about the projects to TUAS