A Model for Product Data in Product Transfer Projects
G00 -> G0 Prestudy
-Initial data described in set
up letter -Making of project proposal
Where are we going?
G2 -> G4 Execution
-Manufacturing Machinery - Manufacturing Tools
-Training
- Manufacturing Instructions -Item data
G4 -> G5 Training
In PU -Readiness For production
Ramp-up -Pilot -0-serie
How do we get there?
Create the project Execute the project
Make the journey safe!
Project Proposal
Project Requirement
Readiness for training in PU
Full production
G0
Start Project
G1 G2 G4 G5
G00
Start Prestudy
Go No-Go
No-Go Go
Go Go
No-Go
No-Go No-Go
G0 -> G1 Project Requirement
-Defining needs and requirement
specification -Defining project
scope
G1 -> G2 Project Plan
-Make up of project plan -Select persons
-Process walk -Estimation of
resources
G5 -> G6 Ramp-Up
-Production Ramp-up -Closing the
project
G6 -> G7 Evaluation
-Comparing project results
to targets, budget and
plans
Project Plan &
Concept
G7 G6
Go
Go Go
Start Planning
Start training
Start ramp-up
Close Project
Retrospective Investigation of
Project
Start Execution
Project Results
Evaluate
Phase:
The most important result of the
phase:
Gate:
No-Go
Appendix I
No-Go